Deployment 1402
AMARSS deployment at James Reserve, June 1, 2005 - June 1, 2010


Deployment Information

Start date: 06/01/05
End date: 06/01/10
Purposes: Measuring microclimate and soil energy balance above and below ground
Location: James Reserve


Group Information

AMARSS


Participants |Leaders are shown in bold.

Kutijama, Kuni
June 1, 2005 - June 1, 2010

Allen, Michael F.
June 1, 2005 - June 1, 2010

Vargas, Rodrigo
June 1, 2005 - June 1, 2010

Taggart, Mike
June 1, 2005 - June 1, 2010

Graham, Eric
June 1, 2005 - June 1, 2010


Technology Information

AMARSS - Automated Mini-Rhizotron


Equipment Information
Item Item Notes# needed, # for backup (source) Dep. Notes

Sensors:
Automated MiniRhizotronDetails1, 0, Installed
Barometric pressure sensorDetails1, 0, Installed
Carbon Dioxide SensorsDetails9, 0, Installed
Relative humidity sensorDetails1, 0, Installed
ThermistorsDetails9, 0, Installed

Motes:
Datalogger - HoboDetails9, 0, Installed


Task Information

There are currently no tasks selected.


Additional Notes

There are no additional notes for this deployment.